Report for July 2018

Report Date
July 2018

Achievements

 

  • Final recommendations made to the business via final report;
  • Project closure report created;
  • Project closed.

 

 

 

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
RAG Commentary
Project closed on 13th July 2018
Change Status
Activity
Approved budget
58.0 days
Activity this month
1.5 days
Activity this year
52.4 days
Activity to date
52.4 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days