Report for December 2018

Report Date
December 2018

Achievements

Issues

  • None

Next Steps

  • Finalise closure report and obtain sign off from stakeholders
  • Close project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Significant
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
New closure date agreed, 1 Feb 2019 was 23 Jul 2018, see PICCL 3.
Activity
Approved budget
36.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.