Report for January 2018
- Report Date
- January 2019
Achievements this period
- Communications & Marketing considering publication of standards and guidelines.
- Large screen templates completed.
- Operating model complete.
- Digital Signage Roadmap complete.
- Pilot of 22" room booking screens extended to LLC, SPS.
- Developer resources have been address immedite issues with screen application.
Issues
None
Next Steps
Communicate project deliverables to sponsors
Publish and Design Templates Guidance and brand chapter C&M.
Project Milestones
| Target Date | Previous Date | Title | Stage | Complete |
|---|---|---|---|---|
| 20-Jul-2018 | No date available | End of Planning | Initiate | Yes |
| 28-Sep-2018 | No date available | Design Standards, Use Cases and Content Types Definition Complete | Execute | Yes |
| 22-Oct-2018 | No date available | Digital Notice Boards & Signage Guidelines Complete | Execute | Yes |
| 08-Nov-2018 | No date available | Target Operating Model Definition Complete | Execute | Yes |
| 23-Nov-2018 | No date available | Digital Display Service Definition Complete | Execute | Yes |
| 14-Dec-2018 | No date available | Complete Design Templates | Execute | Yes |
| 31-Jan-2019 | No date available | Technology Options Paper Complete | Execute | No |
| 14-Feb-2019 | No date available | Closure | Close | No |
- Approved budget
- 30.0 days
- Activity this month
- 4.0 days
- Activity this year
- 28.0 days
- Activity to date
- 28.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days