Report for August 2019

Report Date
August 2019

Achievements

  • Project brief completed and signed off

Issues

  • None

Next steps

  • Establish work on Shibboleth solution
  • Schedule next stages with business partners and vendor

 

Milestones

 

Build Build complete (DEV) 12-Sep-2019
Accept Integration & Acceptance complete 03-Oct-2019
Deliver Delivery 10-Oct-2019
Deliver Delivery sign-off 22-Oct-2019
Close Project closure 31-Oct-2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
33.0 days
Activity this month
3.1 days
Activity this year
3.1 days
Activity to date
4.9 days
Estimate to complete current year
26.8 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.