Report for July 2024

Report Date
July 2024

Section 1: Programme Summary

Programme Manager's Commentary

There are 2 projects in progress:  

  • FIN135 Printing Services System Procurement and Implementation is looking to complete over the next 3 months, as we plan for deploying the system in 2 phases, firstly to staff (internal users), and secondly for external users and students.
  • FIN143 Merchant Acquiring Services Implementation is 

Resource Position

 

Forward Look

 

Section 2: Projects Not Started

Project Info          

Programme Managers Commentary           

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN135

Printing Services System Procurement and Implementation    

Sponsor Funded

RAG Status : GREEN

 

Report by Ben Armstrong for July 2024

This is a restricted project. Those with access will be able to view the report on the project's website.

FIN140

PCI DSS Compliance IT Work

Core Funded

RAG Status : N/A

 

Project Suspended

FIN143

Merchant Acquiring Services Implementation

Core Funded

RAG Status : GREEN

 

Report by Ben Armstrong for July 2024

This is a restricted project. Those with access will be able to view the report on the project's website. 

Section 4: Closed or Withdrawn Projects

Project Info
Project Manager's Commentary

FIN142

Automated Transaction Manager

 

 

 

Ben Armstrong

Date Project Closed: 18-Jan-2024

This is a restricted project. Those with access will be able to view the report on the project's website

Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No