Report for November 2024

Report Date
November 2024

Section 1: Programme Summary

Programme Manager's Commentary

There are 2 projects in progress:  

  • FIN135 Printing Services System Procurement is set to move into closure following a decision from the project sponsor
  • FIN143 Merchant Acquiring Services Implementation is looking to complete in April 2025 with phase 1 completion by December 2024 and phase 2 completion by March 2025.

Resource Position

 

Forward Look

 

Section 2: Projects Not Started

Project Info          

Programme Managers Commentary           

None  

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN135

Printing Services System Procurement and Implementation    

Sponsor Funded

RAG Status : AMBER

Start Date
11-Sep-2020
Planning Date
15-Jan-2021
Delivery Date
TBC
Close Date
TBC

 

Report by Ben Armstrong for November 2024

This is a restricted project. Those with access will be able to view the report on the project's website.

FIN140

PCI DSS Compliance IT Work

Core Funded

RAG Status : N/A

 

Project Suspended (until 24th January 2025)

FIN143

Merchant Acquiring Services Implementation

Core Funded

RAG Status : GREEN

Start Date
05-Feb-2024
Planning Date
28-Mar-2024
Delivery Date
28-Mar-2025
Close Date
28-Apr-2025

Report by Ben Armstrong for November 2024

This is a restricted project. Those with access will be able to view the report on the project's website. 

Section 4: Closed or Withdrawn Projects

Project Info
Project Manager's Commentary

None

 
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation