Report for May 2025
- Report Date
- May 2025
Section 1: Programme Summary
Programme Manager's Commentary
There are 2 projects in progress:
- FIN143 Merchant Acquiring Services Implementation is aiming to complete in July 2025
- FIN144 Discovery for ColdFusion projects has recently started as a small project and is aiming to complete in July 2025
The FIN140 PCI DSS Compliance IT Work project has received approval from the CIO and Finance Director and is aiming to re-start (in June) pending discussion with the proposed core project team.
The programme is awaiting approval for core funding to fund 2 projects for 25/26; these will be ColdFusion replacement projects covering the Insurance application and the Time Allocation Survey (TAS).
Resource Position

Forward Look

Section 2: Projects Not Started
Project Info |
Programme Managers Commentary |
| None |
Section 3: Projects in Progress
Project Info |
Project Managers Commentary
|
|
FIN140 PCI DSS Compliance IT Work Core Funded RAG Status : N/A |
Project Suspended |
FIN143Merchant Acquiring Services Implementation Core Funded RAG Status : GREEN
|
Report by Ben Armstrong for May 2025 This is a restricted project. Those with access will be able to view the report on the project's website. |
Section 4: Closed or Withdrawn Projects
Project Info |
Project Manager's Commentary |
|
FIN135 Printing Services System Procurement and Implementation |
Project closed in Jan 2025 |