Report for May 2025

Report Date
May 2025

Section 1: Programme Summary

Programme Manager's Commentary

There are 2 projects in progress:  

  • FIN143 Merchant Acquiring Services Implementation is aiming to complete in July 2025 
  • FIN144 Discovery for ColdFusion projects has recently started as a small project and is aiming to complete in July 2025

The FIN140 PCI DSS Compliance IT Work project has received approval from the CIO and Finance Director and is aiming to re-start (in June) pending discussion with the proposed core project team.

The programme is awaiting approval for core funding to fund 2 projects for 25/26; these will be ColdFusion replacement projects covering the Insurance application and the Time Allocation Survey (TAS).

Resource Position

 

Forward Look

 

Section 2: Projects Not Started

Project Info          

Programme Managers Commentary           

None  

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN140

PCI DSS Compliance IT Work

Core Funded

RAG Status : N/A

 

Project Suspended

FIN143

Merchant Acquiring Services Implementation

Core Funded

RAG Status : GREEN

 
Delivery Date
04-Jul-2025
Close Date
25-Jul-2025

Report by Ben Armstrong for May 2025

This is a restricted project. Those with access will be able to view the report on the project's website. 

Section 4: Closed or Withdrawn Projects

Project Info
Project Manager's Commentary

FIN135 Printing Services System Procurement and Implementation

Project closed in Jan 2025
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No

Documentation

Not available.