Programme Report for November
- Report Date
- November 2012
Report compiled by Rhian Davies (IS Apps Programme Manager) for Liz Welch (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
AP01-008 eTime Phase 3
Compliance Planning April 2013 Delivery October 2013 RAG Status GREEN | Plan The project is scheduled to start in April 2013, following the eFinancials Upgrade.
Dependencies FIN072 eTime Phase 1 & 2 - this is due to deliver in November 2012. In the following 5 months feedback on the system will be collected and considered during requirements gathering. |
AP12-017 Decommissioning of ERA
Compliance
Planning March 2013 Delivery October 2013 RAG Status GREEN | Plan The project is scheduled to start in March 2013, following the eFinancials Upgrade.
Dependencies This project cannot start until all activity involving ERA is transferred to an alternative solution. |
AP23-004 ePay Reconciliation
Compliance
Planning March 2013 Delivery August 2013 RAG Status GREEN | Plan The project is due to start in March 2013, following the eFinancials Upgrade.
Dependencies
|
AP23-059 eExpenses- Business Case
Compliance
Planning March 2013 Delivery August 2013 RAG Status GREEN | Plan The project is due to start in March 2013, following the eFinancials Upgrade.
Dependencies The project has no dependencies on other activity, however it is dependent on resource availability within Finance, so has been scheduled following the eFinancials Upgrade. |
AP23-055 Rolling out Finance BOXI Reports
Funded Planning n/a Delivery n/a RAG Status GREEN | Plan This project is to be withdrawn.
|
AP23-056 International Bank Validation
Funded Planning April 2013 Delivery December 2013 RAG Status GREEN | Plan The project is due to start in April 2013.
Dependencies |
Sales Invoice Interface Changes
Funded Planning January 2013 Delivery December 2013 RAG Status GREEN | Plan The project is due to start in January 2013. An earlier start date was discussed, however it was deemed to risky due to the high level of activity in the Finance programme in the first few months of the year.
Dependencies The project is related to FIN076 and FIN080. |
AP89-008 FPM for eInvoicing
Discretionary Planning March 2013 Delivery December 2013 RAG Status GREEN | Plan The project is due to start in March 2013, following the eFinancials Upgrade.
Dependencies This project is dependent on the eFinancials Upgrade, due to both resources and software implications. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||
FIN056 (AP Number) eProcurement Scotland - eInvoicing
Category: Funded Milestones --- --- --- RAG Status SUSPENDED
| Report by Rhian Davies for October 2012 Project suspended
| ||||||||||||||
FIN072 (AP01-008) eTime
Category: Compliance Milestones
RAG Status GREEN | Report by Jill Nicoll for November 2012 Achievements in Last Period: Project Deployment signed off Project Closure approved Issues: n/a Next Steps: Final project closure activities will be completed during the first week of the next period.
| ||||||||||||||
FIN076 (AP12-029) Student Finance Channel - Further Developments for Staff and Students
Category: Discretionary Milestones
RAG Status GREEN | Report by Susan McKeown for November 2012 Achievements in Last Period:
Issues:
Next Steps:
| ||||||||||||||
FIN077 (AP Number) Control Account Balancing
Category: /Compliance Milestones
RAG Status GREEN | Report by Sue Woodger for November 2012 Achievements in Last Period
| ||||||||||||||
FIN078 (AP Number) eFin Journal Auto-Upload
Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for November 2012 Achievements last period
Issues
Next Steps
Full details of project activity can be found in the Project Journal
| ||||||||||||||
FIN079 (AP Number) LEAN- Review of Financial Systems
Category: Discretionary Milestones
RAG Status AMBER | Report by Dawn Nicholls for November 2012 Achievements this period
Issues
Next steps
Full details on project activities can be found in the Project Journal | ||||||||||||||
FIN080 (AP Number) Customer Interface Improvements
Category: Discretionary Milestones
RAG Status AMBER | Report by Dawn Nicholls for November 2012 Achievements last period
Issues
Next steps
Full details on project activities can be seen in the Project Journal
| ||||||||||||||
FIN081 (AP Number) Document Management for Finance Applications
Category: Discretionary Milestones --- --- --- RAG Status SUSPENDED | Report by Rhian Davies for October 2012 Project suspended | ||||||||||||||
FIN083 (AP23-003) eFinancials Upgrade
Category: Compliance Milestones
RAG Status RED | Report by Morna Findlay for Rhian Davies for November 2012 Achievements in this period
Outstanding Issues
The project status has been set at RED as the long term printing solution has not yet been approved | ||||||||||||||
FIN084 (AP Number) eStores Rollout Category: Discretionary Milestones
RAG Status GREEN | Report by Dawn Nicholls for November 2012 Achievements last period
Issues
Next steps
Full details of progress can be seen in the project journal
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
FIN082 HMRC Real Time Information
Compliance | Report by [PM] This project was closed/withdrawn on dd-mmm-yy [for closures] Please see the Completion Report / Closure Review for further information [include link]. [for withdrawn] Please see the PRICCL log for further details [include link].
|