Report for July 2018
- Report Date
- July 2018
Report compiled by Andrew Stewart (IS Apps Programme Manager) for David Montgomery(Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
During July, the two active projects were delivered, however, the closure for CSG012 - ESPA will carry forward into early August 2018.
Resources Position
Resources Position
Section Two: Projects Not Started
There are no not started projects currently planned for 17/18.
Project Info | Programme Manager's Commentary |
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||
Category: Discretionary (Sponsor funded) Remaining Milestones
RAG Status : BLUE
|
Report by Nikki Stuart for July 2018 Achievements in the last period
Issues
Next steps
|
||
Fire Management System Category: Discretionary (Sponsor funded) No Remaining Milestones - Project Closed on 13/07/2018 RAG Status : BLUE |
Report by Lee-Ann Simpson for July 2018
Achievements in the last period
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
CSG011 Totara Pilot Category: Discretionary (Sponsor funded) |
Project closed Jan 18. Closure Report can be found at https://www.projects.ed.ac.uk/project/csg011/closure-report |
CSG Learning & Development - Rollout and Further Integration; Category: Discretionary (Sponsor funded) |
Withdrawn following decision not to roll out the L&D system. See closure report for CSG011 above for information. |
CSG013 Fire Management System |
Project Closure on 20th July 2018 |
Attachment | Size |
---|---|
201806-rag.png | 23.86 KB |
201806-resources.png | 31.84 KB |
201807-rag.png | 29.75 KB |
201807-resources.png | 31.77 KB |
201807a-rag.png | 29.85 KB |