Report for January 2022
- Report Date
- January 2022
Report by Muriel Mewissen for Liz Lovejoy (Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
During January, the only ongoing project Xerte Pilot - authorisation and business case is looking to progress the business case following the completion of the technical work and awaiting conformation from LTW whether this is required. LTW is currently reviewing applications that supports SCORM (Sharable Content Object Reference Model) following a request from People & Money, and Xerte is one of the options considered.
The status of the programme is set to GREEN.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - January 2022
Programme Resource to end of January 2022
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
Proposed area for projects this session:
|
CAHSS had a budget of 150 ring fenced days for 21/22. The following allocations have been made:
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||
HSS032 Xerte Pilot - authorisation and business case
RAG StatusGREEN |
Report by Chris Konczak for January 2022Achievements this period
Issues
Next Steps
|
Section Four: Closed Projects
Project Info | Project Manager's Commentary |
---|---|
HSS037 Replacement of ECA Mini Portfolios - Business Analysis |
This project was started in October 2020 and was closed on the 27 August 2021. The Closure Report is available to view. |
Section Five: Programme Risk Register
Risk | RAG | Comments |
---|---|---|
Risk 10: Disruption from the current Novel coronavirus (Covid-19) outbreak | GREEN |
Since 18 March 2020, all staff, as well business partners, moved to working from home during the coronavirus pandemic and UK lockdown which followed on 24 March 2020. A progressive return to campus has started, alongside working from home, in a hybrid fashion from now to May 2022 when working patterns for the future past the pandemic will be agreed. A mixture of home and office working will again be allowed from 31 January 2022. |
Risk 12: Delivery of this CAHSS programme of work for 21/22 is at risk due to BA resourcing pressure from People & Money | RED |
There are three projects scheduled to start this session:
All of them require business analysis. In particular, HSS039 and HSS040 are follow on projects for HSS031 and HSS037 for which it would be more efficient for the previous PM/BA to continue working on these projects. However they been fully allocated to highest priority P&M work COR004/COR007 to end of July 2022. Recruitment is underway for additional BA and PM resources in Project Services. |
Section Six: Programme Meeting Minutes
Date | Comments |
---|---|
18 January 2022 | Programme Review for December 2021 |
16 December 2021 | Programme Review for November 2021 |
16 November 2021 | Programme Review for October 2021 |
13 October 2021 | Programme Review for September 2021 |
15 & 16 September 2021 | Programme Review for July & August 2021 |
27 July 2021 | Programme Review for June 2021 |
15 June 2021 | Programme Review for May 2021 |
24 May 2021 | Programme Review for April 2021 |
14 April 2021 | Programme Review for March 2021 |
11 March 2021 | Programme Review for February 2021 |
10 February 2021 | Programme Review for January 2021 |