Report for May 2022

Report Date
May 2022

Report by Muriel Mewissen for Rick Arnautovic (Portfolio Owner)

Section One: Programme Commentary, RAG and Resources Update

During May, a new procurement project has started to follow HSS037 Replacement of ECA Mini Portfolios:

All projects are reporting a GREEN status.

The status of the programme is set to GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - May 2022

 

Programme Resource to end of May 2022

 

Section Two: Projects Not Started

Project Info Core Funding Budget Allocation

Proposed area for projects this session:

CAHSS had a budget of 150 ring fenced days for 21/22. The following allocations have been made:

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

HSS032 Xerte Pilot - authorisation and business case

 

Milestones

Title Target Date
Closure 28-Mar-2022
 
RAG Status 

GREEN

Report by Chris Konczak for May 2022

Achievements this period

  • Outstanding deliverables reviewed and closure report updated with the outcome, whether achieved or descoped
  • Comments on closure report draft updated to reflect the meeting

Issues

  • None

Next Steps

  • Circulate closure report and close project

 

HSS039 CAHSS WAM Streamlining Phase

 

Milestones

Title Target Date
Project Delivery 30-Jun-2022
Project Closure 29-Jul-2022
 
RAG Status 

GREEN

Report by Susan Ridder-Patrick for May 2022

Achievements this period

  • Project Brief approved
  • Market Analysis completed
  • Change Impact Assessment drafting started
  • Key stakeholders for change assessment identified

Issues

  • None

Next Steps

  • Complete change impact assessment
  • Deliver options appraisal
  • Closure

HSS040 ECA MiniPortfolio Procurement and Implementation

 

Milestones

Title Target Date
Planning 01-Jul-2022
Delivery 28-Feb-2023
Closure 31-Mar-2023
 
RAG Status 

GREEN

Report by Jamie Thin for May 2022

Achievements this period

  • Market research completed for 4 identified suppliers

Issues

  • Project Sponsor needs to confirm available budget - expect the solution will cost approx £50k over 4 years
  • Need Project sponsor to confirm business lead and project team

Next Steps

  • Schedule supplier demos
  • Start 3-quote procurement

 

Section Four: Closed Projects

Project Info Project Manager's Commentary

HSS037 Replacement of ECA Mini Portfolios - Business Analysis

This project was started in October 2020 and was closed on the 27 August 2021. The Closure Report is available to view.

 

Section Five: Programme Risk Register

Risk RAG Comments
Risk 10: Disruption from the current Novel coronavirus (Covid-19) outbreak GREEN

All covid restrictions have now been removed in Scotland.

Risk 12: Delivery of this CAHSS programme of work for 21/22 is at risk due to BA resourcing pressure from People & Money Close All projects for this session have been started.

 

Section Six: Programme Meeting Minutes

Date Comments
18 May 2022 Programme Review for April 2022
21 April 2022 Programme Review for March 2022
17 March 2022 Programme Review for February 2022
22 February 2022 Programme Review for January 2022
18 January 2022 Programme Review for December 2021
16 December 2021 Programme Review for November 2021
16 November 2021 Programme Review for October 2021
13 October 2021 Programme Review for September 2021
15 & 16 September 2021 Programme Review for July & August 2021
27 July 2021 Programme Review for June 2021
15 June 2021 Programme Review for May 2021
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation

Not available.