Report for September 2024

Report Date
September 2024

During September, the FLAC Analysis Project initiation documents were completed and this will start in October

No projects are reporting a RED status

One project is reporting an AMBER status:

Four projects are reporting a GREEN status:

One project is suspended due to the lack of funding

The status of the programme is set to GREEN.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - September 2024

 

Programme Resource to end of September 2024

 

Section Two: Projects Not Started

Project Info Core Funding Budget Allocation

Possible areas of work to be started this session:

  1. FLAC Analysis Project (starting Oct 24)
  2. Support for Targeting Communication (Project start Oct 24)

CAHSS has 150 ring fenced days in 24/25. The following allocations have been made:

Ring Fence:

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

ECA MiniPortfolio Procurement and Implementation (HSS040)

 

Milestones (under review)

Accept Start Remedial Changes UAT 09-Sep-2024
Close Closure - MAJOR MILESTONE 04-Oct-2024
 
RAG Status 

GREEN

Report by Alan Donald for September 2024

 

This is a secure project and only those with access will be able to review the September project report.

 

Peace Agreements Database - Continuous Improvements 22/23 (HSS042)

 

Milestones

Title Target Date
Close 03-Oct-2024
 
RAG Status 

GREEN

Report by Alan Donald for September 2024

 

Achievements this period

  • Fortnightly team meetings continuing
  • Closure report shared with outgoing Programme Manager, Senior Supplier and Project Sponsor
  • Budget confirmed for next project with budget holder
  • Developer has now left the University of Edinburgh, this project will close with a new project to start.

Issues

  • The Project is extended to complete this phase of work. The milestones and budget need to be confirmed.
  • Production resource is limited. Releases will need to planned around this - John Allison taking up with Production
  • Budget was confirmed to the end of March - needs to be adjusted taking the extension into account

Next steps

  • Close Project, start new Project for 24/25
  • Update documentation for handover
  • Ongoing Amnesties DB work

 ISG Services for EFI Launch - Phase 2 (HSS045)

 

Milestones

Milestone Due Date
Helpline & BAU Support model(s) agreed 04-Oct-2024
Complete requirements gathering for EFI (DDI) partners and members 08-Oct-2024
Desk Booking design 08-Oct-2024
Provision of services for EFI (DDI) tenants (MAJOR) 25-Oct-2024
Delivery review 15-Nov-2024
Full ECA resilient link test 29-Nov-2024
Project Closure (MAJOR) 20-Dec-2024
RAG Status 

GREEN

Report by Susan Ridder-Patrick for September 2024

Achievements this period

  • Desk booking pilot continuing under TTU031 Booker project
  • Final support agreement meeting scheduled
  • Innovation centres operating model discussions supporting including service design options
  • Final changes made to project control sheet ahead of the support agreement meeting

Issues

  • ITI CIS VisitEd feedback/communication needed for tenants
  • Milestones change drafted for sponsor approval
  • Scheduling of remaining WAPs installation to be confirmed by BBK/AtkinsRealis
  • No confirmed date from ITI CIS yet for the switch replacement for the resilient link - milestone currently agreed as late November

Next Steps

  • VisitEd feedback/comms from ITI CIS
  • DDI Requirements sign-off to be confirmed as completed by Shared Membership group
  • Complete final update on the project's control sheet for support arrangements for each space in EFI
  • Continue with Eventmap pilot
  • Replace switch and test resilient link

OCS Upgrade (HSS046)

 

Milestones

 

Milestone

Due Date

Creation of TEST and LIVE Rocky servers

6 Sep 2024

TEST environment OCS upgrade completed

30 Sep 2024

LIVE environment OCS upgrade completed

14 Oct 2024

Post deployment support

25 Oct 2024

Close

31 Oct 2024

 

 

 

RAG Status 

AMBER

Report by Sue Woodger for September 2024

Achievements this period

  • Project brief approved 4 Sep 24

Issues

While PM was on annual leave 3 tasks were to be completed

  • Meeting arranged for 13 Sep to agree server design and agent service names (Supplier, Production and Dev Services)
  • Supplier and Production to have agreed Vendor access method
  • Servers ordered and initial work begun

The meeting of 13 Sept did not happen as the Supplier could not make it. We therefore still have to agree the server design, agent names and vendor access. The supplier has been asked to supply dates as to when they can attend a meeting and we will work round those dates.

However, the completion date for the Test server is 30 September 24 and this will not be met. New dates are not yet available until we know when the supplier will engage. Because of this the project will be Amber with regards to time.

 

Next Steps

  • Rearrange meeting with vendor to get agreements on design, agents and vendor access
  • Test servers to be set up
  • OCS upgraded on Test

 

Commentary:  Project is AMBER.

Description: A meeting was arranged during PM leave for 13 Se 24 for vendor to discuss and agree server design and agent service names with Dev Services and Production. A vendor access method was also to be agreed with Production. The meeting did not happen as vendor could not make it.

Impact: Impacts the date for the Test server to be completed as we cannot move forward without vendor input

Plan: Vendor has been asked for dates as to when he can make a meeting. Timelines will be extended

 

 

Section Four: Closed Projects

 

Section Five: Programme Meeting Minutes

Date Comments
15 September 2024 CAHSS Programme Review Meeting - August 2024
AttachmentSize
Image icon sept_2024_forward_look.jpg166.44 KB
Image icon sept_2024_resources.jpg112.61 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation

Not available.