Report for September 2024
- Report Date
- September 2024
During September, the FLAC Analysis Project initiation documents were completed and this will start in October
No projects are reporting a RED status
One project is reporting an AMBER status:
- OCS Upgrade (HSS046) - Supplier availability affecting milestone delivery date
Four projects are reporting a GREEN status:
- ECA MiniPortfolio Procurement and Implementation (HSS040)
- ISG Services for EFI Launch - Phase 2 (HSS045)
- Peace Agreements Database - Continuous Improvements 22/23 (HSS042)
One project is suspended due to the lack of funding
The status of the programme is set to GREEN.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - September 2024
Programme Resource to end of September 2024
Section Two: Projects Not Started
Project Info | Core Funding Budget Allocation |
---|---|
Possible areas of work to be started this session:
|
CAHSS has 150 ring fenced days in 24/25. The following allocations have been made: Ring Fence:
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||
ECA MiniPortfolio Procurement and Implementation (HSS040)
Milestones (under review)
RAG StatusGREEN |
Report by Alan Donald for September 2024
This is a secure project and only those with access will be able to review the September project report.
|
||||||||||||||||
Peace Agreements Database - Continuous Improvements 22/23 (HSS042)
RAG StatusGREEN |
Report by Alan Donald for September 2024
Achievements this period
Issues
Next steps
|
||||||||||||||||
ISG Services for EFI Launch - Phase 2 (HSS045)
RAG StatusGREEN |
Report by Susan Ridder-Patrick for September 2024Achievements this period
Issues
Next Steps
|
||||||||||||||||
RAG StatusAMBER |
Report by Sue Woodger for September 2024Achievements this period
IssuesWhile PM was on annual leave 3 tasks were to be completed
The meeting of 13 Sept did not happen as the Supplier could not make it. We therefore still have to agree the server design, agent names and vendor access. The supplier has been asked to supply dates as to when they can attend a meeting and we will work round those dates. However, the completion date for the Test server is 30 September 24 and this will not be met. New dates are not yet available until we know when the supplier will engage. Because of this the project will be Amber with regards to time.
Next Steps
Commentary: Project is AMBER. Description: A meeting was arranged during PM leave for 13 Se 24 for vendor to discuss and agree server design and agent service names with Dev Services and Production. A vendor access method was also to be agreed with Production. The meeting did not happen as vendor could not make it. Impact: Impacts the date for the Test server to be completed as we cannot move forward without vendor input Plan: Vendor has been asked for dates as to when he can make a meeting. Timelines will be extended
|
Section Four: Closed Projects
Section Five: Programme Meeting Minutes
Date | Comments |
---|---|
15 September 2024 | CAHSS Programme Review Meeting - August 2024 |
Attachment | Size |
---|---|
![]() | 166.44 KB |
![]() | 112.61 KB |