Report Date
October 2024
During September, the FLAC Analysis Project initiation documents were completed and this will start in October
No projects are reporting a RED status
One project is reporting an AMBER status:
Four projects are reporting a GREEN status:
One project is suspended due to the lack of funding
The status of the programme is set to GREEN.
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page .
Programme RAG Overview & Forward Look - October 2024
Programme Resource to end of October 2024
Section Two: Projects Not Started
Project Info
Core Funding Budget Allocation
Possible areas of work to be started this session:
FLAC Analysis Project (starting Oct 24)
Support for Targeting Communication (Project start Oct 24)
CAHSS has 150 ring fenced days in 24/25. The following allocations have been made:
Ring Fence:
Section Three: Projects in Progress
Project Info
Project Managers Commentary
ECA MiniPortfolio Procurement and Implementation (HSS040)
Milestones (under review)
RAG Status
GREEN
Report by Alan Donald for October 2024
This is a secure project and only those with access will be able to review the September project report.
Peace Agreements Database - Continuous Improvements 22/23 (HSS042)
Milestones
Title
Target Date
Close
03-Oct-2024
RAG Status
GREEN
Report by Alan Donald for October 2024
Achievements this period
New project started
Closure report shared with outgoing Programme Manager, Senior Supplier and Project Sponsor
Budget confirmed for next project with budget holder
Issues
The Project is extended to complete this phase of work. The milestones and budget need to be confirmed.
Next steps
ISG Services for EFI Launch - Phase 2 (HSS045)
Milestones
RAG Status
AMBER
Report by Susan Ridder-Patrick for October 2024
Achievements this period
Desk booking pilot continuing under TTU031 Booker project
Support arrangements for every space in EFI agreed and project control sheet completed
Requirements signed off for DDI tenants and members for EFI and Bayes. Usher pending.
Closure Report draft in progress
Issues
ITI CIS VisitEd feedback/communication needed for tenants
Scheduling of remaining WAPs installation to be confirmed by BBK/AtkinsRealis - feedback from ITI CIS pending
No confirmed date from ITI CIS yet for the switch replacement for the resilient link - milestone currently agreed as late November
Next Steps
VisitEd feedback/comms from ITI CIS
Replace switch and test resilient link
Schedule of remaining WAPs installation
Continue with Eventmap pilot
Usher requirements sign-off
OCS Upgrade (HSS046)
Milestones
Milestone
Due Date
Creation of TEST and LIVE Rocky servers
13-Nov-2024
TEST environment OCS upgrade completed
22-Nov-2024
LIVE environment OCS upgrade completed
14-Jan-2025
Post Deployment support and DSOR
28-Jan-2025
Close
31-Jan-2025
RAG Status
GREEN
Report by Sue Woodger for October 2024
Achievements this period
Finally managed to meet with supplier and an agreement on the build was reached along with new dates for the project agreed
Servers have now been ordered - 1-2wk lead time so expected at the beginning of November
Originally were expecting to have to build
2 x Test MariaDB (mariadb-ocs-kb1test & mariadb-ocs-at1test)
1 x Test App Server (ocs-app-test)
2X Live MariaDB (mariadb-ocs-kb1live & mariadb-ocs-at1live)
1 x Live App Server (ocs-app-live)
But DevTech have since discussed with the Supplier and are now planning to use Docker containers and this has reduced the servers down to two
ocsinventory-test
ocsinventory-live
Issues
Due to supplier being unable to attend the initial meetings the build of the servers was delayed – but they have now been ordered
Revised milestones were therefore agreed and submitted to AppsReview
Next Steps
Completion of server build
Supplier to update OCS on Test
CAHSS to test the TEST environment
Peace Agreements Database – Continuous Improvements 24/25 (HSS048)
Milestones
TBC
RAG Status
GREEN
Report by Alan Donald for October 2024
Achievements this period
Project Started
New developer recruited, due to start on 18th November
Project Brief completed and to be circulated
Python decommissioning process agreed with INF169 - not charged to project
Issues
Next steps
Continue fortnightly meetings
Report budget position to Sponsor
Onboard new developer
Tidy Jira backlog
Milestone
Due Date
Delivery (Analysis)
13 Dec 2042
Close
22 Dec 2042
RAG Status
GREEN
Report by Sue Woodger for October 2024
Achievements in last period
Initiation approved at Apps Review
Project Brief completed and noted at Apps Review 24/10/24
Revised estimate at planning issue log 1 approved at Apps Review 24/10/24
Analysis has started
Issues
New dates agreed at planning to account for delay in initiation submission
was
now
Delivery (Analysis)
15/11/2024
13/12/2024
Close
29/11/2024
22/12/2024
A meeting is taking place 5 November with sponsor to discuss project scope following first meeting with business lead and SME. Expectation was that the project would be doing analysis for CRM not just file store
Next Steps
Scope confirmed
Analysis ongoing
Section Four: Closed Projects
Section Five: Programme Meeting Minutes
Programme Status
RAG Status
Has formal escalation taken place?
No