Report for March 2025

Report Date
March 2025

Section One: Programme Commentary, RAG and Resources Update

Commentary

Four projects are reporting a GREEN status

No projects are reporting a RED or AMBER status

1 new project  started this month - HSS050 - Programme, Course and Cohort Mailing List Solution  which is now in planning

Ring-Fenced Days/Core Funded:

Sponsor Funded :

 

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Programme RAG Overview & Forward Look - March 2025

 

 

Programme Resource to end of March 2025

 

Section Two: Projects Not Started

 

Project                                            Programme Manager's Commentary
   

Section Three: Projects in Progress

ECA MiniPortfolio Procurement and Implementation  (HSS040)

Milestones

Stage Milestone Due Date Previous Date Complete  
Close Closure - MAJOR MILESTONE 10-Apr-2025 14-Feb-2025 No

view

RAG Status

Green

Report by Alan Donald for March 2025

Achievements

  • Cycle for submissions now complete, business handled issues between admissions and supplier during the submission period
  • Assessors reviewing submissions
  • Project Brief circulated to key stakeholders - lessons learned updated follow discussions with previous Project/Programme Manager, and Business Analyst

Issues

  • Budget to be adjusted with Project Sponsor
  • Closure Milestone to be updated

 

Next Steps

  • Complete Deployment Checklist - Handover meeting with Production arranged
  • Update Closure Report based on feedback from key stakeholders
  • Close Project

OCS Upgrade (HSS046)

 

Milestones

Close (MAJOR MILESTONE)

02-Apr-2025

 

 

RAG Status 

GREEN

Report by Sue Woodger for March 2025

Achievements in last period

  • OCS was upgraded on LIVE on 11 March 25
  • HSS tested on LIVE
  • Post-deployment period ended on 28 March 25
  • The old server was switched off during this period (18 March 25)
  • Closure report has been circulated for approval

Issues

  • During post-deployment period the following issues were corrected

    • Docker image build now updated by supplier on 2.12.3 tag. The other tag will be completed shortly for their next patching
    • Advice on backing up from supplier
    • Some agents were found to be manually configured so a temporary fix was put in place and the sponsor is starting a project to update these agents.

Next Steps

  • Closure report approved
  • Project closed

 

 

REDCap Installation Project (HSS047)

 

Milestones
Milestone Due Date
End of Planning 10-Apr-2025
TEST and LIVE infrastructure build complete    25-Aor-2025
Integration testing complete complete 28-Apr-2025
LIVE build complete 30-Apr-2025
DSOR 14-May-2025
Project Close 16-May-2025
RAG Status

GREEN

 

Report by Chris Konczak for March 2025

Achievements in Last Period

  • Project brief updated and now completed
  • Business have completed the REDCap Installation form for the licence so Dev Tech are now able to download the software
  • Discussions and meetings carried out with other areas of the University that use REDCap in order to ascertain the likely costs Production will incur post go-live.
  • Approved planning milestone date change at Apps Review - change to 10/04/2025

Issues

  • After a meeting with MVM and which gave an overview into the support that REDCap requires post go-live, Production had requested that the brief is not put into Apps Review until the project gets extra support budget approval of 7 days. This will take into account weekly patching and bi-annual upgrades that are required. Prior to the meeting with MVM it was initially thought that the original KSR budget would be sufficient.
  • The planning has been delayed to 10/04/2025 as the CAHSS Programme Owner will need to approve the extra 7 days KSR support budget. The Programme owner is on annual leave until the start of April.

Next Steps

  • Meeting with Programme Owner to discuss the KSR budget increase
  • Project brief to be signed off by project team and Apps Review
  • REDCap software to be downloaded and build commenced

 

Peace Agreements Database – Continuous Improvements 24/25  (HSS048)

 

Milestones
Stage Milestone Due Date  
Initiate Project Initiated 04-Oct-2024

view

Execute Fortnightly Sprints Start - MAJOR MILESTONE 31-Oct-2024

view

Execute New Senior Software Developer starts 18-Nov-2024

view

Execute Handover between Software Developers completed 29-Nov-2024

view

Initiate End of Planning - MAJOR MILESTONE 30-Jan-2025

view

Build New Staging Environment Completed 14-Feb-2025

view

Deliver Amensties DB Upgrade Completed & Decommissioning Started 28-Feb-2025

view

Deliver TAD and SDS Updated 21-Mar-2025

view

Deliver End of Final Delivery Sprint (MAJOR MILESTONE) 27-Mar-2025

view

Close Project Closure - MAJOR MILESTONE 31-Mar-2025

view

RAG Status

GREEN

Report by Alan Donald for March 2025

Achievements this period

  • Fortnightly sprints prioritised
  • Staging environment build completed and deployment underway, ITI fixing issue related to environment
  • Amnesties Database deployed onto new Python infrastructure - Python decommissioning process passed to Production- not charged to project
  • Production Handover started - Document review started
  • Additional Developer working on project in March, focus on moving and updating Amnesties DB
  • Extending Project into April to allow for latest coding release

Issues

  • N/A

Next steps

  • Continue fortnightly meetings
  • Report budget position to Sponsor
  • Complete Staging environment build
  • Extend project milestones
Free Legal Advice Centre (FLAC) - File Store Analysis (HSS049)
 

Revised milestones have been submitted to this weeks Apps Review

 

Current

Will be

Delivery: Analysis

18-Feb-2025

14-Mar-2025

Close

21-Feb-2025

19-Mar-2025

RAG Status 

GREEN  as change control submitted to Apps Revise for extended closure date

Report by Sue Woodger for March 2025

Achievements in last period

  • None this month

Issues

  • Project closure has been held up this month as the project sponsor has been on extended leave  and HSS wanted to wait until he was back to close the project. The closure was therefore pulled from its original submission and will be resubmitted to Apps Review at the beginning of April when project sponsor is due to return

Next Steps

  • Project closed

 

Section Four: Closed Projects

 

Project Info Project Manager's Commentary
Peace Agreements Database - Continuous Improvements 22/23 Closed December 2024
ISG Services for EFI Launch - Phase 2 Closed December 2024
ISG Services for EFI Launch - Phase 2 (HSS045) Closed December 2024

  Peace Agreements Database - Continuous Improvements 22/23 (HSS042)

Closed December 2024
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation

Not available.