Report for March 2025
- Report Date
- March 2025
Section One: Programme Commentary, RAG and Resources Update
Commentary
Four projects are reporting a GREEN status
No projects are reporting a RED or AMBER status
1 new project started this month - HSS050 - Programme, Course and Cohort Mailing List Solution which is now in planning
Ring-Fenced Days/Core Funded:
- Free Legal Advice Centre (FLAC) - File Store Analysis | Project Management - Awaiting sign off for closure
- OCS Upgrade | Project Management - Awaiting feedback for closure
Sponsor Funded :
- REDCap Installation Project (HSS047) - Milestone moved as decision needed on production support
- Peace Agreements Database – Continuous Improvements 24/25 (HSS048) - Closure Milestone to move out to end of April due to some additional developer time required
- ECA MiniPortfolio Procurement and Implementation (HSS040) - Production handover in progress
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Programme RAG Overview & Forward Look - March 2025

Programme Resource to end of March 2025

Section Two: Projects Not Started
| Project | Programme Manager's Commentary |
Section Three: Projects in Progress
|
ECA MiniPortfolio Procurement and Implementation (HSS040) Milestones
RAG Status Green |
Report by Alan Donald for March 2025Achievements
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||
|
RAG StatusGREEN |
Report by Sue Woodger for March 2025Achievements in last period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||
|
REDCap Installation Project (HSS047)
Milestones
RAG StatusGREEN
|
Report by Chris Konczak for March 2025Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||
|
Peace Agreements Database – Continuous Improvements 24/25 (HSS048)
Milestones
RAG StatusGREEN |
Report by Alan Donald for March 2025Achievements this period
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||||||||||
Free Legal Advice Centre (FLAC) - File Store Analysis (HSS049)Revised milestones have been submitted to this weeks Apps Review
RAG StatusGREEN as change control submitted to Apps Revise for extended closure date |
Report by Sue Woodger for March 2025Achievements in last period
Issues
Next Steps
|
Section Four: Closed Projects
| Project Info | Project Manager's Commentary |
| Peace Agreements Database - Continuous Improvements 22/23 | Closed December 2024 |
| ISG Services for EFI Launch - Phase 2 | Closed December 2024 |
| ISG Services for EFI Launch - Phase 2 (HSS045) | Closed December 2024 |
|
Peace Agreements Database - Continuous Improvements 22/23 (HSS042) |
Closed December 2024 |