Report for August 2023

Report Date
August 2023

 

Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge and Rona Smith (GaSP), Kate Brook (D&A), Edd McCracken (CAM), Shane Collins (SRA) and other interested business area owners.

Section One: Programme Commentary, RAG and Resources Update

Commentary

The new 23/24 session starts with five ongoing projects.

During August, USG021 Results Days and Clearing Helpline 2023 was succesfully delivered. Projects continue to progress well with a high level of activities on some projects. Two project are reporting a RED RAG status:

Three projects are reporting a AMBER status due to lack of availability of the stakeholders. 

The overall status for the USG Portfolio Projects programme is AMBER.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

The start of year budget position is recorded in 2023/24 - Start of Year USG Portfolio Budget.

 

Forward Look - August 2023

 

Resources to end August 2023

Note that USG027 D&A portal continuous improvements 23/24 is not yet listed in the table above. It is a sponsor funded project and is included in the 2023/24 - Start of Year USG Portfolio Projects Programme Budget programme record.

 

Section Two: Projects Not Started

Project Programme Manager's Commentary

The following two projects will be started in 23/24:

 

 

Section Three: Projects in Progress

Project Info

Project Managers Commentary

USG016 Signal to PURE Application

Category: Discretionary

 

Milestones

Target Date Title
09-Jun-2023 Go Live
16-Jun-2023 Delivery Sign Off
30-Jun-2023 Project Closure

 

RAG Status

AMBER

Report by Alan Donald for August 2023

Achievements

  • SDD Review completed and additional items to be added.
  • Additional user restrictions to be placed in app to prevent all staff from being able to access
  • Developer has prioritised updates following SDD review, to be completed ASAP

Issues

  • Milestone dates out of date, to be updated

Next Steps

  • Complete Development following SDD review
  • Go Live
  • Close Project

USG021 Results Days and Clearing Helpline 2023

Category: Compliance

 

Milestones

Major and key milestones as follows: -

Target Date Title
29-Sep-2023 Project Closure (MAJOR)
 
RAG Status

GREEN

Report by Ailsa Glass for August 2023

Achievements

  • The call centre was successfully set up, configured and tested in advance of the SQA Results Day (08/08/23) 

  • The Results Helpline and Clearing call centres ran well on SQA Results Day with 453 calls answered across the day 

  • The call centre was successfully set up, configured and tested in advance of the A Levels Results Day (17/08/23) 

  • The Results Helpline ran well on A Results Day with 948 calls answered across the day 

  • All delivery milestones have been successfully delivered and noted at Apps Review 

  • Positive feedback has been received from stakeholders about the new location as well as how smoothly the call centres operated. Surveys have been produced to gather this feedback for incorporation into the Closure Report 

  • The Closure Report has been drafted and issued to the project team for review 

Issues

  • A few minor technical issues were encountered on Results Day but did not impact the ability to answer calls. These issues have been logged in the Lessons Learned Log and will be picked up with the supplier for resolution in advance of next year’s call centres 

Next Steps

  • Closure Report to be reviewed and signed off 

  • Project closure

USG023 University Policy Repository - SharePoint

Category: Discretionary

 

Milestones

Title Target date
Start Development - Library to Website API 11-Sep-2023
UAT Sign Off - repository 20-Sep-2023
Policy Repository QA begins 25-Sep-2023
Reporting and views design complete 29-Sep-2023
Reporting and views build complete 27-Oct-2023
Launch Policy Repository 03-Nov-2023
Development complete - Library to Website API 01-Dec-2023
Delivery sign-off 08-Dec-2023
UAT Start - directory 15-Jan-2024
UAT Sign Off - directory 16-Feb-2024
Launch policy directory 29-Mar-2024
Project Closure - Major 19-Apr-2024
RAG Status

RED

Report by Chantal Reilly for August 2023

Achievements

  • Developer resource secured and started work on project
  • Users provided feedback on processes
  • Process for uploading policies finalised
  • Introductory training provided for policy leads
  • UAT preparations completed
  • Reporting requirements begun
  • RACI drafted

Issues

  • Process and form design has been more complex and taken longer than expected due to MVP approach 
  • Reduced capacity within Service Management due to competing priorities
  • Difficult to prepare thoroughly for UAT given capacity issues
  • High burn-rate through budget

Next Steps

  • UAT
  • UAT review and fixes
  • API design and build
  • Planning governance
  • Budget review

 

 

 

 

 

  

USG024 Student Recruitment and Admission CRM Integration

Category: Discretionary

 

Milestones

Target Date Title
15-Jun-2023 Planning
31-Oct-2023 Delivery
30-Nov-2023 Closure
RAG Status

AMBER

Report by Muriel Mewissen for August 2023

Achievements

  • Service request submitted with CRM supplier to set up Test environment.
  • New PM assigned.

Issues

  • Low activity over August due to staff leave and the need to replace the Project Manager following their departure from UoE
  • Delay in planning

Next Steps

  • Reboot of the project in September with the new PM and the CRM service manager who will be back from parental leave.
  • Produce planning documents.
  • Continue with technical configuration.

USG025 Enabling Curriculum Transformation

Category: Discretionary

 

Milestones

 

RAG Status

RED

Report by Richard Bailey for August 2023

 

This is a restricted project. Those with access will be able to view the August Report on the project website.

 

Section Four: Closed Projects

Project Info Project Manager's Commentary

N/A

No project has been completed this year yet.
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No

Documentation

Not available.