Report for November 2023

Report Date
November 2023

Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge and Rona Smith (GaSP), Kate Brook (D&A), Edd McCracken (CAM), Shane Collins (SRA) and other interested business area owners.

Section One: Programme Commentary, RAG and Resources Update

Commentary

In November, all projects are reorting an AMBER RAG status due to delays and work extending past the existing timeframe.

The overall status for the USG Portfolio Projects programme is AMBER.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

The start of year budget position is recorded in 2023/24 - Start of Year USG Portfolio Budget.

 

Forward Look - November 2023

 

Resources to end November 2023

The programme budget increased by 220 days to 713 days, see Programme Change record 147.

 

Section Two: Projects Not Started

Project Programme Manager's Commentary

The following two projects will be started in 23/24:

 

 

Section Three: Projects in Progress

Project Info

Project Managers Commentary

USG016 Signal to PURE Application

Category: Discretionary

 

Milestones

Target Date Title
27-Oct-2023 Go Live
31-Oct-2023 Delivery Sign Off
07-Nov-2023 Project Closure

 

RAG Status

AMBER

Report by Alan Donald for November 2023

Achievements

  • Bug fix signed off
  • CAB Approval received

Issues

  • N/A

Next Steps

  • Add application to ABACUS
  • Go Live
  • Close Project

USG023 University Policy Repository - SharePoint

Category: Discretionary

 

Milestones

Target Date Title
01-Dec-23 Development complete - Library to Website API
15-Jan-24 UAT Start - directory
28-Feb-24 UAT Sign Off - directory
29-Mar-24 Launch policy directory
05-Apr-24 Delivery sign-off
19-Apr-24 Project Closure

 

RAG Status

AMBER

Report by Sue Woodger for November 2023

Achievements

  • Change of project manager - Sue Woodger took over from Catherine Hetherington wef 14/11/23
  • Policy Repository launched on 13 Nov 23
  • Quality Assurance was completed
  • TAD completed and successfully reviewed by AppsMan and TechMan
  • Communications plan for delivery kicked off
  • Lewis Allan and Kate Robertson from GaSP now on board as part of the project team
  • API and front end development is completed in Dev

Issues

  • End-to-end UAT design to be completed by PM. This is difficult as the current PM did not write the requirements but Claire Bradford has given some help
  • There has been some confusion around what comms need to go out around delivery of the system and they appear to be complicated so PM has kicked off a communications plan
  • The quality assurance was patchy. Linda Criggie has checked for missing mandatory fields and listed for GaSP to follow up. Also Finance have still to confirm creation of the pdf’s
  • PM has reviewed the budget and expenditure for the project on taking over and it is sitting as overspent  - an issue will be raised for approval from programme manager and programme owner

Next Steps

  • SDD for repository to be started
  • Accessibility statement to be written
  • Views to be completed - have been started
  • Review the RACI that had been previously parked
  • API and front end development to be moved into Test wb 5 Dec 23
  • Walkthrough of system to take place 7 Dec 23 with all parties
  • End-to-end UAT design to start
  • Supporting Guidance (to Policy ‘for policies’) awaiting sign off within GaSP – then needs to go on Repository Training/Support page

 

USG024 Student Recruitment and Admission CRM Integration

Category: Discretionary

 

Milestones

Target Date Title
27-Oct-2023 End of Planning
09-Nov-2023 Dynamics Environment Set Up Complete
21-Nov-2023 Gecko App Set Up Complete
30-Nov-2023 DotDigital Environment Set Up Complete
01-Dec-2023 Test Integrations between Gecko, DotDigital and Dynamics
15-Dec-2023 Complete Integrations between Gecko, DotDigital and Dynamics
19-Jan-2023 Identify DPIA Needs
26-Jan-2024 Integration Documentation Complete
09-Feb-2024 Delivery - Major
09-Feb-2024 Presentation to SRFSG
23-Feb-2024 Closure - Major
RAG Status

AMBER

Report by Alan Donald for November 2023

Achievements

  • Dynamics environment set up by supplier
  • Gecko setup done with supplier
  • Project Brief circulated for sign off

Issues

  • Delay in planning completion
  • Delay in providing Dynamics test environment from supplier as they work on an image for use by the wider University. Due to completed w/b 30th Nov

Next Steps

  • Sign off Project Brief
  • Continue with technical configuration.
  • Confirm December team meeting dates
  • Confirm February SFRSG Meeting

USG025 Enabling Curriculum Transformation

Category: Discretionary

 

Milestones

 

RAG Status

AMBER

Report by Richard Bailey for November 2023

 

This is a restricted project. Those with access will be able to view the November Report on the project website.

 

Section Four: Closed Projects

Project Info Project Manager's Commentary

USG021 Results Days and Clearing Helpline 2023

This project started in April 2023 and was closed on 29 September 2023. The Closure Report is available to view.
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No

Documentation

Not available.