Report for Jan 2015
- Report Date
- January 2015
Report compiled by Jamie Thin (IS Apps Programme Manager)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
--
The two not-started proposals for 2014-15 have been withdrawn
--
Section Two: Projects Not Started
Project Info | Project Managers Commentary |
AP45-027 PURE - Integration with EUCLID (PGR student data) - Phase 2 - PGR students as Users (Self-service) Discretionary (Core) RAG Status WITHDRAWN | This project has been withdrawn |
AP45-051 Research Explorer redevelopment (RCUK / REF Open Access compliance) Annual Small enhancements Discretionary (Core) RAG Status WITHDRAWN | This project has been withdrawn |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||
RES059Category: Compliance
Milestones
RAG Status GREEN | Report for January 2015 by Sally Hayward Achievements in Last Period
Issues
Next Steps
| ||||
RES060Category: Compliance Milestones
RAG Status GREEN | Report for January 2015 by Sally Hayward Achievements in Last Period
Issues
Next Steps
| ||||
SAS001 PURE Database Migration Category: Compliance Milestones
RAG Status GREEN | Report for January 2015 by Sally Hayward Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP34-028 Migration to Infinite Oracle SOA Suite 11g Compliance RAG Status WITHDRAWN (and CLOSED) | This project has been withdrawn now that the RMAS Contract has been awarded. |
RES045 RMAS Replacement [Procurement Phase] Funded RAG Status CLOSED | This Project has been delivered and is now closed See Completion Report for further information |