Monthly Report

Report Date
July 2025
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Usher Institute Enhanced AV Project
Code
AV3096
Programme
ISG Learning and Teaching Spaces: CMVM (AV)
Management Office
ISG PMO
Project Manager
John Power
Project Sponsor
Alan Gilchrist
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
01-Jan-2026
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Sep-2025
Overall Priority
Normal

Documentation