- Report Date
- September 2018
Achievements
- Deployment signed off by project team
Issues
Next steps
- Approved budget
- 30.0 days
- Activity this month
- 2.2 days
- Activity this year
- 7.3 days
- Activity to date
- 15.3 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days