Report for September 2018

Report Date
September 2018

Achievements

  • Deployment signed off by project team

Issues

  • None

Next steps

  • Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
30.0 days
Activity this month
2.2 days
Activity this year
7.3 days
Activity to date
15.3 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
JIRA Upgrade
Code
COM040
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Bill Lee
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
18-Jun-2018
Planning Date
29-Jun-2018
Delivery Date
28-Aug-2018
Close Date
05-Oct-2018
Programme Priority
5
Overall Priority
Normal
Category
Compliance

Documentation