GDPR Preparation for Applications Project Closure

The new GDPR legislation came into force on 25 May 2018.  The  GDPR Preparation for Applications project  (COM042) provided support for the work required across Application Services to ensure compliance with the  legislation.

The project delivered:

  • Internal register for Apps Services

  • Assessment of  services which required privacy notices (and progressed publication of these)

  • Evaluation of other work required for Apps owned services for May 2018 and beyond

  • Recommendations for Apps Services Privacy Impact Assessments

  • Evaluation of working practices and recommendations for future work to make changes to these.

The project also developed an action plan for colleagues within Apps to work together to ensure compliance with GDPR aligned to the areas identified.  These actions have been ongoing throughout the project and will continue beyond the closure of the project.

Project Info

Project
GDPR Readiness for Applications Division Services
Code
COM042
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Emma Mcnab
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
17-Nov-2017
Planning Date
09-Feb-2018
Delivery Date
25-May-2018
Close Date
05-Oct-2018
Overall Priority
Normal
Category
Compliance

Documentation