- Report Date
- April 2020
Achievements in Last Period:
- Completed project implementation plan
- Supplier led user training and familiarisation scheduled for Thursday 14th May
- Contact established with supplier helpdesk regarding Single Sign On configuration
Issues:
- Due to the lack of Development Technology resource availability, it has not been possible to progress the Single Sign On configuration
Next Steps:
- Formally extend project to incorporate system implementation
- Commence technical configuration regarding Single Sign On
- Initial user training to be completed
- Commence system configuration
- Establish communication strategy for system users
- Approved budget
- 55.0 days
- Activity this month
- 0.3 days
- Activity this year
- 21.8 days
- Activity to date
- 39.3 days
- Estimate to complete current year
- 15.3 days
- Estimate to complete future years
- 1.8 days