- Report Date
- August 2020
Achievements in Last Period:
- Technical Configuration
- Single Sign-On has been configured
- Email configuration is on-going
- Pilot Project
- The Pilot project is underway with representatives from Procurement and ISG Project Services
- A training session was held for members of the pilot project regarding the risk creation process
- System Configuration
- A data mapping exercise has commenced to map the required data from the current Risk Register spreadsheet to the system fields
- Work is on-going to configure the system
Issues:
Next Steps:
- Technical Configuration
- Complete email configuration
- System Configuration
- Complete data mapping regarding capturing risk related data
- Continue wider system configuration to ready system for University roll-out
- Pilot Project
- Populate system with new risks
- Further training to be scheduled to regarding Reporting and System Dashboards
- Analysis of risk management process flow and associated emails to be undertaken
- Approved budget
- 55.0 days
- Activity this month
- 5.0 days
- Activity this year
- 5.0 days
- Activity to date
- 51.6 days
- Estimate to complete current year
- 10.1 days
- Estimate to complete future years
- 0.0 days
This article was published on