Report for August 2020

Report Date
August 2020

Achievements in Last Period:

  • Technical Configuration
    • Single Sign-On has been configured
    • Email configuration is on-going   
  • Pilot Project
    • The Pilot project is underway with representatives from Procurement and ISG Project Services 
    • A training session was held for members of the pilot project regarding the risk creation process
  • System Configuration 
    • A data mapping exercise has commenced to map the required data from the current Risk Register spreadsheet to the system fields
    • Work is on-going to configure the system 

Issues:

  • No issues

Next Steps:

  • Technical Configuration 
    • Complete email configuration 
  • System Configuration 
    • Complete data mapping regarding capturing risk related data 
    • Continue wider system configuration to ready system for University roll-out 
  • Pilot Project 
    • Populate system with new risks
    • Further training to be scheduled to regarding  Reporting and System Dashboards
    • Analysis of risk management process flow and associated emails to be undertaken 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
55.0 days
Activity this month
5.0 days
Activity this year
5.0 days
Activity to date
51.6 days
Estimate to complete current year
10.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Risk Management System Procurement
Code
CSG015
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Chris Maclean
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
11-Feb-2019
Planning Date
05-Apr-2019
Delivery Date
28-Oct-2020
Close Date
31-Mar-2021
Programme Priority
7
Overall Priority
Higher
Category
Discretionary