Report for June 2022
- Report Date
- June 2022
Achievements this Period
- MS COMPLETE DATA MIGRATION TEST/CHECK - completed as planned by 17 Jun
- USER ACCEPTANCE MS completed as planned by 17 Jun
- The DATA MIGRATION/IRM CONFIG LIVE MS completed by 20 Jun
- New users added to the IRM 20 Jun
- Following the live config, the Business Lead(Fraser)did identify some additional data to be migrated and that was completed immediately.
- Handover to Support 30 Jun
- Approval to close the project confirmed by Alex Hutchison, Fraser Macdonald, Alasdair Macleod(Alan Hughes) and Jason Murphy(24 Jun).
Issues
no new issues
Next Steps
- Project closure report approval - still three approvers to follow up with.
- Target Apps Review 7th or 14th Jul for formal closure.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days