Report for January 2017

Report Date
January 2017

Achievements in Last Period

  •  Project brief completed & signed off

Issues and Risks

  • None reported

​Next Steps

  • Commence work on design
  • Deliver prototype of website

Milestones

28-Feb-2017 Design & Analysis complete Design
28-Mar-2017 Delivery of website Deliver
14-Apr-2017 Project closure Close

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
28.0 days
Activity this month
2.7 days
Activity this year
4.1 days
Activity to date
4.1 days
Estimate to complete current year
23.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Digital Transformation Website
Code
DTI001
Programme
Digital Transformation - Engagement and Other Projects
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Mark Ritchie
Current Stage
Close
Status
Closed
Start Date
16-Dec-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
12-May-2017
Overall Priority
Higher
Category
Discretionary