Delivery Milestone Report for 10/11/20
- Report Date
- November 2020
Delivery Milestone Report for 10th November 2020
Project Status
RAG Status - Green
Overview
Delivery of a virtual tour solution for SRA that provides, through an interactive map containing information hotspots and rich media assets, a space and place representation of the University and its environs. This will be a key tool at a time when physical visits are not possible and likely to be constrained for some time.
Next Delivery Milestone: UoE Sign Off Service Wrapper - 11-Nov-2020
RAG Commentary
- The site was officially launched / is live 02-Nov-2020.
- Work underway to apply a Service Wrapper.
- Works underway agreeing publication and site content creation BAU processes. This may now be agreed to extend beyond the main Project life cycle.
- A draft closure report has been created ready for review 16-Nov-2020.
- Project Closure now predicted 20-Nov-2020.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days