Current project status Report Date RAG Budget Effort Completed Effort to complete January 2021 BLUE 152.0 days 155.0 days 0.0 Content Status Closed Current Stage Close Start Date Monday, 20 January 2020 Planning Date Monday, 23 March 2020 Delivery Date Thursday, 17 December 2020 Close Date Friday, 8 January 2021 Project information Project Code ENT205 Programme ITI - Enterprise Services (ENT) Session 20/21 19/20 Organisational Unit IS IT Infrastructure Project Management Office (if relevant) ISG PMO Responsibility IT Infrastructure Project Category Discretionary Project Classification Run Project Type Infrastructure Project Size Small Project Complexity Standard Alignment to Strategy 2030 and Adaptation & Renewal Team (ART) People Funding Source ITI Core Programme Priority 3 Overall Priority Normal Student Impact Project deliverables will have no impact on students