Report for May 2017

Report Date
May 2018

Achievements in Last Period

  • Project closure report submitted to 18th May WIS and accepted.

Issues

  • None.

Next Steps

  • None.
Target Datesort descending Previous Date Title Stage Complete  
21-Jul-2017 No date available End of Planning Plan Yes

view

09-Aug-2017 No date available End of Analysis / Design Analyse No

view

18-Sep-2017 No date available Start UAT Accept Yes

view

19-Jan-2018 03-Nov-2017 Readiness / Approval to Go-Live (indicative) Accept Yes

view

05-Feb-2018 13-Nov-2017 Go-Live (indicative) Deliver Yes

view

16-Feb-2018 01-Dec-2017 Deployment Sign-off (indicative) Deliver Yes

view

02-Mar-2018 15-Dec-2017 Closure (indicative) Close Yes

view

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
258.0 days
Activity this month
2.0 days
Activity this year
273.4 days
Activity to date
316.2 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Archibus Upgrade
Code
EST098
Programme
Estates Systems & Technology Maintenance (EST)
Management Office
ISG PMO
Project Manager
Chris Orrell
Project Sponsor
Grant Ferguson
Current Stage
Close
Status
Closed
Start Date
17-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
18-May-2018
Programme Priority
2
Overall Priority
Normal
Category
Discretionary