Asset Management - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2018 GREEN 200.0 days 217.2 days 3.8
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 24 July 2017
Planning Date
Friday, 13 July 2018
Delivery Date
Thursday, 9 May 2019
Close Date
Friday, 19 July 2019
Project information
Project Code
EST099
Programme
Estates Business Operations Optimisation Programme (EOO)
Session
18/19
17/18
16/17
Organisational Unit
Estates Department
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Discretionary
Project Classification
Grow
Funding Source
Sponsor Funded
Programme Priority
2
Overall Priority
Normal
Student Impact
Project deliverables will be used by staff on behalf of students