2017/18 statement published and promoted.

Working group meeting held - discussion on how to achieve more impact. Further research and work on implementation plan pending.

Staff training target is high (1000, whereas only 99 so far) - have requested it to be mandatory on Key Commercial Policies assessment.

Student training has no uptake yet, but review of approach is planned.

Noting as amber because of challenges around staff and student training uptake, but no serious risk and target was not for this year only.

Project Status
RAG Status
Overall
AMBER
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Modern Slavery (Research, Working Group and Statements)
Code
FTP002
Programme
SRS - Fairness in Trade and Sustainable Procurement (FTSP)
Project Manager
Alexis Heeren
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
03-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a