Report for May 2018
- Report Date
- May 2018
Report Date
- May 2018
Achievements in Last Period
- Project initiated
- Brief agreed / signed off
- Work packages initiated
- Agreement with Production (application management) to pick up a number of current support based issues, time boxed to 3 days
Issues
- None
Next Steps
- Complete work packages
- Deploy to LIVE
Milestones
| Target Date | Title | Stage |
| 18-May-2018 | Planning | Plan |
| 25-May-2018 | Design | Design |
| 08-Jun-2018 | Build | Build |
| 15-Jun-2018 | Integration / Acceptance | Accept |
| 22-Jun-2018 | Deployment | Deliver |
| 06-Jul-2018 | Closure | Close |
- Approved budget
- 18.0 days
- Activity this month
- 7.6 days
- Activity this year
- 9.5 days
- Activity to date
- 9.5 days
- Estimate to complete current year
- 7.8 days
- Estimate to complete future years
- 0.0 days