Report for July 2018
- Report Date
- July 2018
Report Date
- July 2018
Achievements in Last Period
- Two more production issues were identified since deployment to live, neither of these were as a result of the additional works requested by the Business, but were thought to be further items that were now noticeable as a result of fixing the time boxed support based issues on behalf of Application Management. The Developer has a booking to complete these works w/c 30/07/2018. These are being tracked in risk #5: Pre-Existing LDAP Issue
Issues
- None
Next Steps
- Sign off / deployment of fixes to the additional two production issues
- Close Project
Milestones
| 07-Aug-2018 | Deploy Bug Fixes | Deliver |
| 10-Aug-2018 | Closure | Close |
- Approved budget
- 18.0 days
- Activity this month
- 2.1 days
- Activity this year
- 18.6 days
- Activity to date
- 17.4 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days