Report for October 2015
- Report Date
- October 2015
Achievements in Last Period
- Minor alterations made following feedback on the Calculator from HR community
- Implementation Plan and Deployment Checklists completed
- JIRAs raised for final changes for deployment week which include updating to the new payscales
Issues
- None
Next Steps
- Complete pre-deployment JIRAs (new payscales and few wording changes)
- Deploy
- Delivery Sign-off
- Close
24-Nov-2015 | Deploy HR Reward Calculator to LIVE |
01-Dec-2015 | Deployment Sign-off of HR Reward Calculator |
08-Dec-2015 | Closure |
- Approved budget
- 13.0 days
- Activity this month
- 2.0 days
- Activity this year
- 9.0 days
- Activity to date
- 9.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days