January Report
- Report Date
- January 2017
Achievements in Last Period
- Meeting held with Dev Tech resource to provide estimation of effort for SRM Activity - overall 25 days effort in total
- Project plan updated for SRM Activity and resource requests updated on ASTA
Issues
- Update from ITI regarding SRM issue - they are currently in the process of testing out some diagnostic steps that the vendor has them working through. They should know more towards end of January.
- Dev Tech resource request not assigned as Resource Manager indicated that another possible solution has been discussed with Project Sponsor and ITI
- Project Sponsor advised that the discussion is around a stretched cluster, this is quite a different solution and much more resilient. Timescales are to potentially buy and setup a stretched cluster over the next 6 to 12 months. Project Sponsor will raise at next ITI / Apps meeting and review with Head of Development Services to not progress SRM work.
-
Agreement with project sponsor to continue with database failover work for WIKI
-
Proposed milestone dates to be reviewed with project team and Service Manager for WIKI
Next Steps
- Plan Wiki failover activity for Dev Environment and agree Dev Tech resource
-
Request resource and VM Build
The project status is RED due to possible change to scope and progress on the project, proposed milestones need to be reviewed and agreed.
TBC | SRM Testing Complete |
28/02/17 TBC |
|
15/03/17 TBC |
|
28/03/17 TBC |
|
04/04/17 TBC |
|
11/04/17 TBC |
- Approved budget
- 100.0 days
- Activity this month
- 1.3 days
- Activity this year
- 11.1 days
- Activity to date
- 19.2 days
- Estimate to complete current year
- 63.5 days
- Estimate to complete future years
- 0.0 days