July Report

Report Date
July 2016

Achievements in Last Period

  • Project brief updated and reviewed with Tech Man, Dev Tech and Apps Man presentatives including estimates and dates
  • Project brief submitted to WIS for approval, include ITI as a stakeholder

Issues

  • Look at other potential candidates such as (WIKI and Learn) that are on dedicated infrastructure not on AppsLive
  • Forecasted resource budget in 15/16 of 25 days not fully used therefore may require additional effort in 16/17. This will be re-estimated on completion of first failover application.

Next Steps

  • Review of Top and Medium Priority Services to be completed for Service resilience e.g full, partial or non
  • Plan Events Booking failover activity for Dev

The project status is GREEN

 

12-Aug-2016

Review of Top & Medium Priority Services

21-Sep-2016

Priority Service (1) Development Failover complete

05-Oct-2016

Priority Service (1) Test Failover complete

02-Nov-2016

Priority Service (2) Development Failover complete

18-Nov-2016

Priority Service (2) Test Failover complete

30-Nov-2016

Priority Service (2) Live Failover complete

05-Dec-2016

Delivery

16-Dec-2016

Closure

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
3.0 days
Activity this year
8.0 days
Activity to date
8.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
83.0 days

Project Info

Project
Service Resilience Capability
Code
INF119
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
06-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
18-May-2017
Programme Priority
7
Overall Priority
Normal
Category
Discretionary

Documentation