Report for May 2018
- Report Date
- May 2018
Achievements in Last period
- Met with all stakeholders. Started workflows for DIU
Issues
- Was apparent at meeting with curators that all their workflows were different so will need to set up separate meetings with each of them. PM to work out id=f additional days are required.
- Workshop for to-be is not until 12 June which will put back delivery plus as-is writes not completed by milestone date . PM to review dates
Next Steps
- Write ups of as-is interviews
- To-be workshop scheduled for 12 June
The project status is AMBER
Milestones
|
01-Jun-2018 |
Business Analysis sign off |
|
15-Jun-2018 |
|
|
20-Jun-2018 |
Delivery Review |
|
29-Jun-2018 |
- Approved budget
- 50.0 days
- Activity this month
- 10.9 days
- Activity this year
- 15.5 days
- Activity to date
- 15.5 days
- Estimate to complete current year
- 34.3 days
- Estimate to complete future years
- 34.3 days