Report for July 2018
- Report Date
- July 2018
Achievements in Last period
- As-is interviews are continuing
- Carry-over of 16 days into 18/19 submitted to WIS 31 July 18
Issues
- Due to higher priority project commitments PM has been unable to complete the as-is write up or complete the recommendations and a piccl has been created to carry over into 18/19
Next Steps
- Complete as-is interviews
- Write up recommendations and high level requirements and present these back to Library
- Close
The project status is GREEN as revised dates have been agreed
Milestones
|
31-Aug-2018 |
Delivery: Business analysis sign off |
|
7-Sep-2018 |
- Approved budget
- 50.0 days
- Activity this month
- 7.2 days
- Activity this year
- 34.0 days
- Activity to date
- 34.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 16.0 days