Report for August 2018
- Report Date
- August 2018
Achievements in Last period
- As-is interviews completed
- Delivery: Business analysis sign off: Recommendations and high level requirements presented to Kirsty Lingstadt, Joe Marshall, Norman Roger and Karen Stirling. All were happy with the report and will be meeting to discuss how they can take the first 3 points forward and disseminate to Library staff
- Point 1 was to
Digitise your processes
- Point 2 was to
Streamline your systems
- Point 3 was to
Improve metadata and catalogues
- Point 4
Promote yourselves
requires wider university website integration - Point 5
Enhance the student experience
is for the future – points 1-3 need to be happen first
- Point 1 was to
Issues
- Higher priority project commitments, end of year and sheer volume of write ups meant that PM has been unable to complete the as-is write ups
Next Steps
- Complete as-is write ups
- Close
The project status is GREEN
Milestones
|
7-Sep-2018 |
- Approved budget
- 50.0 days
- Activity this month
- 12.0 days
- Activity this year
- 12.0 days
- Activity to date
- 45.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days