Report for October 2018

Report Date
October 2018

Achievements in Last period

  • As-is interviews completed and written up
  • Project closed 7 September 2018 (PM was absent in September and  project report not completed but programme report notes project as closed)

 

Issues

  • None

Next Steps

  • None

 

The project status is CLOSED

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
12.0 days
Activity this year
12.0 days
Activity to date
45.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Digitisation (Library) Process Analysis
Code
ISG012
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Kirsty Lingstadt
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
02-Mar-2018
Planning Date
12-Apr-2018
Delivery Date
31-Aug-2018
Close Date
07-Sep-2018
Overall Priority
Normal
Category
Discretionary

Documentation