Report for January 2025

Report Date
January 2025

Achievements This Period

  • sprint 31 closed
  • new acting PM assigned

Planned Activity

  • sprint 32 ending 5th Feb

 

Milestones

 

Milestone Date
Start 09-May-2023
Plan 01-May-2023
Deliver  30-Jul-2025
Close 31-Jul-2025
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
sprint to continue to Jul
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Research Data Service Systems : Service Upgrade
Code
LUC070
Programme
Library & Collections - Digital Library BAU (LUCDL)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Robin Rice
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
09-May-2023
Planning Date
01-May-2023
Delivery Date
05-Dec-2025
Close Date
19-Dec-2025
Overall Priority
Normal
Category
Compliance

Documentation

Not available.