- Report Date
- May 2025
Achievements This Period
- sprint 36 - completed
- new project brief - drafted
- new milestones in place
-
Issues and Risks
Next Steps
- sprint 37 by 28th May
- new project brief approved
- new milestones
- report back on COSIGN issue for DSPACE 6 and plan accordingly
- initial review of UX for Dspace 8
- complete review and classification and prioritisation of backlong
-
-
Future Milestones
| Milestone |
Date |
| Sprint 37 |
28-May-2025 |
| Deliver |
5-Dec-2025 |
| Close |
19-Dec-2025 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days