Report for July 2025
- Report Date
- July 2025
Achievements This Period
- new project brief approved - done
- Sprints 39 and 40 - done
- DV 4.1.8 Release - released
Issues and Risks
- COSIGN must be replaced by 30th August - COSIGN replaced in Live - expect 100% confirmation on 20th August when system is updated
Next Steps
- review of UX and Design for Dspace 8
- Sprint 41 and 42
Future Milestones
| DataShare : Design Updated | 30-Sep-2025 |
| DataShare : Upgrade to DSpace 8 | 05-Dec-2025 |
| DataShare : Backlog completed | 05-Dec-2025 |
| DataVault : Backlog completed | 05-Dec-2025 |
| Agile Method : New Ways of Working in Place | 05-Dec-2025 |
| Close | 19-Dec-2025 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days