Report for September 2025
- Report Date
- September 2025
Achievements This Period
- Sprint 43 and 44 - done
- review of Home Page design - done
- review of Submission Page design - done
- possible release of accessibility release - pending
Issues and Risks
- COSIGN must be replaced by 30th August - COSIGN replaced in Live - expect 100% confirmation on 20th August when system is updated
- strike action in Sept
- DV down for three weeks when ACF closes
Next Steps
- Sprint 45,46,47
- UX changes
- possible release of accessibility release
Future Milestones
| DataShare : Design Updated | 30-Sep-2025 |
| DataShare : Upgrade to DSpace 8 | 05-Dec-2025 |
| DataShare : Backlog completed | 05-Dec-2025 |
| DataVault : Backlog completed | 05-Dec-2025 |
| Agile Method : New Ways of Working in Place | 05-Dec-2025 |
| Close | 19-Dec-2025 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days