Report for October 2025
- Report Date
- October 2025
Achievements This Period
- Sprint 45,46,47 - 45 and 46 achieved
- Accessibility release for DataShare - achieved
- UX changes - under definition
- possible release of accessibility release - not scheduled
Issues and Risks
- COSIGN must be replaced by 30th August - COSIGN replaced in Live - expect 100% confirmation on 20th August when system is updated
- strike action in Sept
- DV down for three weeks when ACF closes
Next Steps
- Sprint 47 48
- Next release of DataShare Dspace 8
- User testing for DSpace 8
- Documentation for Dspace 8
- Set DV processes to keep libraries, code, framework, etc updated
- UX design changes next release of DS
- dates for PEN testing of DV
For DataShare -
I would assume the next one would be a major release so a 5.0. (Aiming for before end of year) given its an update from Dspace 6.1? to 8.2
All the various work done during the sprints for enhancements and fixes – yes relating to DSpace8 migration epic
The UX design improvements currently under way - yes Include processes to ensure we do not fall behind on the components (DB, Java libraries, etc) – No – we have nothing lined up for this as yet as Robin said our process for this is relating to DV.
And - All the user testing and documentation updates relating to DSpace8 migration which have to be completed still – just about to start. – these are all LUC070-211 – 214.
Future Milestones
| DataShare : Design Updated | 30-Nov-2025 |
| DataShare : Release of DSpace 8 | 05-Dec-2025 |
| DataShare : Backlog completed | 05-Dec-2025 |
| DataVault : Backlog completed | 05-Dec-2025 |
| Agile Method : New Ways of Working in Place | 05-Dec-2025 |
| Close | 19-Dec-2025 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days