Current project status

Report Date RAG Budget Effort Completed Effort to complete
September 2025 GREEN 61.0 days 33.7 days 27.0
Content
Status
In Progress
Current Stage
Execute
Start Date
Friday, 19 January 2024
Planning Date
Wednesday, 5 March 2025
Delivery Date
Friday, 28 August 2026
Close Date
Wednesday, 30 September 2026
Project information
Project Code
LUC074
Programme
Library & Collections - Digital Library BAU (LUCDL)
Session
25/26
24/25
23/24
Organisational Unit
Library and University Collections
Project Management Office (if relevant)
ISG PMO
Responsibility
Library and University Collections
Overall Priority
Normal