- Report Date
- November 2019
Achievements this period
- Limited progress due to project manager's annual leave.
- Have received response from clinical contact in Forth Valley that eduroam is indeed now installed in the hospital and that students are using it.
Next Steps
- Create a suitable PC build configuration for the PAEP library and install on the computers on site.
- Receive suggested options for restoring eduroam connectivity in NHS Lanarkshire.
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days