April 2020

Report Date
April 2020

Achievements this period

  • Project has been suspended due to a reliance on NHS IT staff for much of the work and an inability to access certain buildings.
  • Requests for assistance from clinicians and studentsĀ in NHS areas will be dealt with on a best efforts basis under business as usual, until effort from NHS IT staff can be released from their other duties due to COVID-19.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
BLUE
RAG Commentary
Project is being suspended, as limited progress can be made whilst NHS IT staff have other priorities and an inability to access certain buildings.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Connectivity - Off-campus
Code
MVM125
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
04-Feb-2019
Planning Date
n/a
Delivery Date
28-Oct-2021
Close Date
29-Oct-2021
Overall Priority
Normal

Documentation