March 2019

Report Date
March 2019

Achievements this period

  • Two existing PCs (with new hard drives purchased) have been identified for installation in the Princess Alexandra Eye Pavilion (PAEP) library and these will have broadband dongles installed behind a secure panel to stop anyone removing them.  As PCs will not be connected to University network, configuration needs to be designed and agreed prior to PCs being deployed.
  • Khipu have confirmed their quoted cost is correct and that they had always quoted for a 1 year supported service.  Need to find out what happens after the year of support is up - i.e. will hardware be removed, will additional costs be incurred to keep the service running.
  • Have tried to organise a meeting with NHS Lanarkshire IT staff to discuss current issues with their offering of eduroam, so that a proposed solution can be generated and implemented.

Next Steps

  • Create a suitable PC build configuration for the PAEP library and install on the computers on site.
  • Chase up meeting with NHS Lanarkshire IT staff.
  • Confirm what 1 year service contract with Khipu would include and what happens after that year.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Connectivity - Off-campus
Code
MVM125
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
04-Feb-2019
Planning Date
n/a
Delivery Date
28-Oct-2021
Close Date
29-Oct-2021
Overall Priority
Normal