Project Status Reports

Title Report Date Time Cost Scope Overall Change
September 2018 September 2018 BLUE BLUE BLUE BLUE
July 2018 July 2018 GREEN GREEN GREEN GREEN
June 2018 June 2018 GREEN GREEN GREEN GREEN
May 2018 May 2018 GREEN GREEN GREEN GREEN
Report for April 2018 April 2018 AMBER GREEN GREEN AMBER
March 2018 March 2018 AMBER GREEN GREEN AMBER
February 2018 February 2018 AMBER AMBER GREEN AMBER

Project Info

Project
Upgrading of teaching spaces 2017/18
Code
MVM127
Programme
MVM Learning and Teaching (MVMLAT)
Management Office
ISG PMO
Project Manager
Alan Gilchrist
Project Sponsor
Alan Gilchrist
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
26-Feb-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Sep-2018
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation