Report for 30 June 2017
- Report Date
- June 2017
Achievements
- No work undertaken on this project this month
Issues
- No issues
Next Steps
- Process scans to ensure all available online (work undertaken August, September 2017)
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days