- Report Date
- March 2019
Achievements
- Sponsor confirmed on December 21 that all projects should be closed in January
- Close documents prepared, awaiting confirmation that project can be closed - meeting with sponsor scheduled for April 11, 2019
Issues
Next steps
Milestones
- Approved budget
- 34.0 days
- Activity this month
- 0.0 days
- Activity this year
- 8.2 days
- Activity to date
- 28.1 days
- Estimate to complete current year
- 19.6 days
- Estimate to complete future years
- 0.0 days